Building C · Artesian Football Complex

MSD of Martinsville High School, 1360 E. Gray St., Martinsville, Indiana · For GM Development · Built by GT Investments, LLC · Plans by D B Tarr and Company

Renderings

Aerial from the southwest: the new 80' × 170' locker room building, with the re-skinned softball locker room in front
Aerial from the northeast, toward the softball field
Eye level from the south lawn
Eye level from the north (restroom side), with the asphalt drive
Interior cutaway with the roof and ceilings off
Top view of the site: walks, parking, fence and the Artesian Well

Interactive 3D model

The model is built from the final-plans IFC (2026), plus the site sheets A703–A706 and X10, laid on Indiana lidar ground and aerial imagery. Drag to orbit, and pinch or scroll to zoom. The side panel has finishes, layers, Foundation, Exterior concrete, rooms, interior/MEP/site views and walk mode. Click a part to see its product info. Right-click or long-press a part to hide it, hide everything of its type, or show all hidden parts. Walls between you and the room fade out automatically; you can turn this off under Display. ASSUMED The plumbing comes from the IFC and is a guide only: what was built is different.

Open the model full screen ? How to use the 3D model

The Building

Size & code

  • New football locker room building, 80' × 170' (13,600 SF), 1 story
  • Existing softball locker room 1,920 SF, re-skinned, with a 64 SF (8' × 8') porch addition
  • Occupancy A-3, construction type V-B
  • Final inspection 8/26/2026, with a partial certificate of occupancy for the new locker room. First home game 8/28/2026.

Shell

  • GPB post-frame shell: 2×6 walls, 80' trusses at 4' o.c., 3.5/12 gable roof
  • Ivory GPB Board & Batten siding, soffit, porch ceiling, fascia and downspouts
  • Burnished Slate G-Rib 40-year 29 ga roof, roof trim and gutters; black standing seam on the softball concession porch
  • G10 liner on the walls and ceiling with R38 blown fiberglass
  • 48" brick wainscot by L&L Masonry (Change Order #1) on an 8" CMU brick ledge
  • 8" painted CMU interior walls
  • 6" seamless gutters and one row of snow guards
  • Brick color still ASSUMED (Reed to send)

Rooms (IFC)

100 Corridor, 101 Women's RR, 102 Men's RR, 103 Restroom, 104 Shower, 105 Storage, 106 Vestibule, 107 Coach's Office, 108 Vestibule, 109 Visitor's Locker Room, 111 Mechanical & Electrical, 112 Team Meeting Room, 113 Equipment Storage, 114 Artesian Room, 115 Corridor, 116 Corridor, 117 Janitor, 118 Passage, 119 Artesian Locker Room, 120 Restroom, 121 Shower, 122 Restroom, 123 Official's Room, 124 Football Coach's Office, 125 Break, 126 Lockers, 127 Head Coach Office, 128 Corridor, 129 Storage, 130 Restroom, 130B Chase, 131 Laundry, 132 Training, 133 Chase, 134 Chase, 135 Chase, 136 Chase, 137 Chase

Existing softball building: E101 Locker Room, E102 Storage, E103 Concessions, E104 Office, E105 Mechanical, E106 Storage, E107 Restroom, E108 Coridor, E109 Vestibule, E110 Dugout

Mechanical & plumbing

  • 3 Alpha Aire II DOAS units (8 ton) by AllTrades
  • Radiant heat in the floors (benches can't be anchored more than 1" deep)
  • Culligan Hi-Flo 3e water softener
  • Sloan G2 8111-1.6 and 8186-1.0 flush valves; all other fixtures per the AllTrades "Josh Specs" set
  • Laundry: Milnor 30022T6X washer, Milnor M758V dryer, Clean Cycle lint trap + Greenheck inline blower (Loomis Bros.)

Floors

  • Polyurea / epoxy flake with a polyaspartic top coat (TAK); the showers get ADA curbs
  • Milliken carpet planks in the offices
  • Polished concrete by TAK Floor Coatings over Christmas break 2026 (X3 plan rooms + north restrooms), after a test spot in the officials' room

Doors & security

  • Hollow metal doors and frames (CDF) with SFIC hardware (IN Door & Hardware), re-cored by the school to Medeco
  • Keyed removable mullions on the double doors (Change Order #2)
  • APTEK access control on 8 doors, 9 cameras and about 40 network drops

Site

Paving (A704–A706)

  • 4" concrete walks on 2" #11 stone
  • HMA: full-depth, mill and 1.5" resurface, and surface seal with crack repair
  • Stalls 9' o.c., ADA aisles, and a no-parking zone
  • Concrete parking curbs pinned about 24" to center (ASSUMED)

Utilities (X10)

  • 2" gas line lowered for CenterPoint, with a new gas meter
  • Duke electric service; electrical box north of the ticket booth lowered (Live Wire Consulting / LWC)
  • Fiber handhold and conduit repaired; APTEK/Galaxy One pulled new fiber

Fence & landscape

  • Wrought iron fence and main gates (Parker Fencing, Camby, IN)
  • Chain link privacy fence around the HVAC units and the electrical service
  • Artesian Well: two rock tiers with a pump, and alternating red and yellow mums
  • Retention pond: not being done (not in scope, per Reed 10/26/26)

The ground is Indiana 2016–2020 lidar (bare earth) with the current IndianaMap aerial, which predates construction. Grading next to the building is ASSUMED (no grading plan on file).

FF&E, finishes & products

Brands, models and colors come from Reed's invoices, the selection manuals, the spec sheets and email. Anything not confirmed is marked ASSUMED.

CategoryItemBrandModel / specColorQtyLocationLinksSource / status
Exterior shellMetal roofGraber Post Buildings (GPB)G-Rib 40 yr 29 ga w/ Therma Guard, 3.5/12 gable, 1 row snow guard per sideBurnished Slate (roofing, roof trim and gutters)80x170 bldgRoofsiteGPB contract #71682; Reed Tarr email 10/26/26
Exterior shellMetal sidingGraber Post Buildings (GPB)GPB Board & Batten 10" 26 ga w/ house wrap + 7/16" OSB; Board & Batten soffit and porch ceilingIvory (siding, soffit, downspouts, fascia)Exterior wallssiteGPB contract #71682; Reed Tarr email 10/26/26
Exterior shellInterior liner walls + ceilingGraber Post Buildings (GPB)G10 10 yr 29 ga liner; ceiling liner w/ R38 blown fiberglassWhite ASSUMEDMechanical / non-ACT areassiteGPB contract #71682
ASSUMED
Exterior shellGutters + downspoutsGraber Post Buildings (GPB)6" seamless incl. accessoriesGutters Burnished Slate; downspouts IvoryEavesGPB contract #71682; Reed Tarr email 10/26/26
Exterior shellBrick wainscotL&L Masonry LLC (installer)Brick on perimeter, base flashing/weeps/ties; height raised 40" to 48" (Change Order #1)"Bricks to match existing building" - brick name/color not on filePerimeterNew building baseL&L quote #949 (11/21/2025); Change Order #1 (3/31/26)
Brick name ASSUMED (Reed will send separately)
Exterior shell8" CMU wallsL&L Masonry LLC8" CMU 10-12 ft, rod & cell 6 ft o.c., bond beam, bull nose at doors/cornersPainted (SW ProMar 200)Interior bearing wallsL&L quote #949
Exterior shellAluminum frame windowsASSUMED via GPB/Indy Glass26" x 64" aluminum frame windowColor ASSUMED4Per Change Order #3Change Order #3 (3/31/26)
ASSUMED
DoorsHollow metal doors + framesCDF Distributors18 ga galvannealed polystyrene-core HM doors, Steelcraft hinge prep, 161 lock prep; 16 ga 3-piece knockdown masonry frames; 4-1/2" ball-bearing NRP hinges 26DPainted ASSUMEDPer door scheduleAll doorssiteCDF quotes QB-09435555 / QB-09517142; Martinsville Door Schedule
DoorsDoor hardwareIndiana Door & Hardware Specialties17 cylindrical SFIC locks, 31 closers (8 w/ stop arm), 23 exit devices w/ lever trim, 11 Medeco exterior cylinders, 19 interior cylinders; re-cored by school to MedecoSatin chrome / 26D ASSUMEDsee qtyAll doorsIN Door & Hardware inv. 140696AA (5/21/26) + 5 follow-up invoices
Lock/closer brand ASSUMED
DoorsKeyed removable mullionsCDF Distributors4900X keyed removable mullion set 84" (6 non-rated + 1 fire rated); 3901 rim cylinder 26D x726D7All double doors except #132siteCDF quote 450721; Change Order #2
DoorsAccess control + cameras + networkAPTEK (contract w/ GM Development)Access control 8 doors, 9 cameras (Cat 6 plenum), ~40 network drops, Aruba switch8 doors / 9 camsBuilding CsiteAPTEK quotes #002421 V3, #002495 V1
FlooringEpoxy flake floor + showersTAK Floor CoatingsDiamond grind CSP 2-3, MVB epoxy base, 1/4" full-broadcast flake, polyaspartic top coat, polyurea joint fillFlake: OASIS custom blend4,963 SF + 518 LF jointsRestrooms, showers, locker rooms (X3 plan)siteTAK invoice #75 (6/19/26); X3 Floor Covering 11-20-25
FlooringCarpet tile (planks)MillikenColor Field Patina PAT108 (Dim Stone) + PAT249-52 (Billion)Dim Stone / Billion~1,030 SFOffices (carpet plank on X3 10-21-26)siteWagler Floor & Design inv. 4419 (7/25/26)
FlooringCarpet adhesive + reducerMilliken / SchluterMilliken Non-Reactive Standard Modular Adhesive; Schluter Vinpro-U reducer 9/32"Reducer: brushed nickelCarpet edgessiteWagler inv. 4419
FlooringCove baseJohnsonite (adhesive)4" cove base; Johnsonite 960 wall base adhesiveCharcoal35 LFCarpet roomsWagler inv. 4419
Base brand ASSUMED
FlooringPolished concrete (planned)TAK Floor CoatingsMechanical grind + polish; test spot in officials room; rest over Christmas break 2026ClearPer X3 Floor Covering 10-21-26: Corridors 100, 115, 116, 128; Passage 118; Vestibules 106, 108; Laundry 131; Lockers 126; Official's Room 123; Artesian Room 114; Team Meeting Room 112; Equipment Storage 113 (aisle); plus north restrooms 101 Women's RR and 102 Men's RR per Kyle (not hatched on the plan)Corridors, team rooms, north restroomsmanualMartinsville AFC - Floor Covering 10-21-26 (from Reed); Reed Tarr email 10/26/26
Planned (Christmas break 2026)
FlooringADA shower curbsBrand not on fileADA-compliant rollover shower curb systemAll showersShowersReed emails 8/31 + 10/1/26
ASSUMED
Walls / ceilingsPaintSherwin-WilliamsSW ProMar 200Base: GPB Grey; accents: Duct Blue and Positive Red. Duct Blue and Positive Red are school custom colors mixed by Sherwin-Williams to the school's standards; they have no paint codes.Interior walls (accent locations per X10)siteSelection Manual 5-29-26; Reed Tarr email 10/26/26
GPB Grey SW number not on file
Walls / ceilingsAcoustic ceilingArmstrong (via Brown Brothers Lumber)15/16" drop grid; 24x24 Fissured 949 (general) / Fine Fissured 928 (high moisture)WhiteCeilingssiteBuilding C - Final Selections.pdf / Selection Manual 5-29-26
CaseworkCabinetsCabinets To GoHampton Pewter shaker: 13 BC36, 4 BC30, 2 DC318, 3 DC324, 5 SB36, 4 LC1884 pantry, 12 WC3630, 5 WC3618, 4 WC3030, 3 WC2430, 2 WC1830 + fillers/toe kick/scribeHampton Pewter57 boxesBreak, team meeting, training, equipment, laundry, coach, officialssiteCabinets To Go SO92422268 (6/11/26)
CaseworkCountertopsStoll Bros. LumberLivingStone solid surface w/ 4" backsplash, field measured + installed; WB24-BLK brackets x4 prLivingStone Crystal IceArtisan, break, team meeting, training, equipment, laundry, coach, officialsStoll Bros 2606-C28955 + 2607-C30284; Reed Tarr email 10/26/26
CaseworkCabinet knobsBrown Brothers Lumber1-3/16" diameter knobSatin nickelCabinetsBuilding C - Final Selections.pdf / Selection Manual 5-29-26
Toilet accessoriesToilet partitionsMcMaster-Carr (ordered via GPB)1" solid plasticDark Blue recommended (match softball locker room) - ASSUMEDRestroomssiteBuilding C - Final Selections.pdf / Selection Manual 5-29-26; Allowance sheet (Div 10)
ASSUMED
Toilet accessoriesMirrorBobrickB-165-1824Stainless18RestroomssiteMartinsville - Bathroom Items; Selection Manual
Toilet accessoriesBaby changing stationASI (American Specialties)ASI 9012 surface-mounted plasticGrey ASSUMED2 installedPublic restroomssiteTotal Restroom TR-303115856; Reed Tarr email 10/26/26
Color ASSUMED
Toilet accessoriesShower seatsBobrickB-5181 reversible folding shower seat (L x3, R x7)Phenolic10ADA showerssiteTotal Restroom TR-303115856; Bathroom Items
Toilet accessoriesDressing seatBobrickB-51911ADA dressingsiteBathroom Items list
Supplier ASSUMED
Toilet accessoriesSanitary napkin disposalBobrickB-270 surface-mountedStainless7Women / unisexsiteTotal Restroom TR-303115856
Toilet accessoriesWaste receptacleBobrickB-367-60 12 gal surface-mountedStainless13RestroomssiteTotal Restroom TR-303115856
Toilet accessoriesToilet tissue dispenserScott Essential (Kimberly-Clark)Coreless twin jumbo roll KCC09608Black15ToiletssiteTotal Restroom TR-303115856
Toilet accessoriesPaper towel dispenserScott Essential (Kimberly-Clark)Manual hard roll towel dispenser (KCC46253 per selection)Black ASSUMED13RestroomssiteTotal Restroom TR-303115856; Bathroom Items
Toilet accessoriesSoap dispenserScott EssentialsManual liquid hand soap dispenser (92145)12LavatoriessiteBathroom Items sheet 2 / Selection Manual
Supplier ASSUMED
Toilet accessoriesGrab barsJones Stephens1-1/2" satin concealed flange: G13118 (18") x32, G13130 (30") x10, G13136 (36") x14, G13142 (42") x14Satin stainless70ADA toilets / showerssiteGrabbars.com GB-32729, GB-33177, GB-33827, GB-34320
PlumbingWater closetsAllTrades "Josh Specs" setPer Josh Specs (AllTrades); Madera FloWise spec sheet kept for referenceWhiteper planRestroomssite · manualJosh Specs; Reed Tarr email 10/26/26
Exact bowl model per Josh Specs folder
PlumbingToilet flush valves (as built)SloanSloan G2 8111-1.6 (1.6 gpf)Chromeall WCsRestroomssiteReed "Plumbing Issues - AFC" 10/5/26; Reed Tarr email 10/26/26
PlumbingUrinal flush valves (as built)SloanSloan G2 8186-1.0 (1.0 gpf)Chromeall urinalsRestroomssiteReed Tarr email 10/26/26
PlumbingUrinalsAllTrades "Josh Specs" setUT447E washout urinalWhiteper planRestroomssiteJosh Specs; Reed Tarr email 10/26/26
PlumbingLavatoriesZurnZ5340 wall-hung vitreous china (AllTrades Josh Specs)Whiteper planRestroomsmanualJosh Specs; Reed Tarr email 10/26/26
PlumbingLavatory faucetsProFloPFWSC3007 single handle 1.2 gpm (AllTrades Josh Specs)Chromeper planLavatoriessiteJosh Specs; Reed Tarr email 10/26/26
PlumbingShower valves / headsOlympiaTD-2372-ADA i2 ADA handheld shower (AllTrades Josh Specs)Chromeper planShowersmanualJosh Specs; Reed Tarr email 10/26/26
PlumbingDouble bowl sinksCompass Manufacturing003-513 33x22x6" double bowlStainlessper planBreak / trainingSpecs/Double Bowl Sinks; Josh Specs per Reed Tarr email 10/26/26
Confirm model against Josh Specs folder
PlumbingUtility sink + wall faucetPer AllTrades Josh Specs setStainless / chromeTraining / laundryJosh Specs per Reed Tarr email 10/26/26
Model per Josh Specs folder
PlumbingWater softenerCulliganHi-Flo 3e HCE-300-3 w/ hard water bypass; 30x50 brine tank, 3/4" valve; 3/4" vacuum breaker; 3" SS NPT flow meter1Mechanicalsite · manualCulligan inv. 6489609 (5/27/26)
PlumbingBoiler / water heatingNavienNFC-175 (from IFC)per IFCMechanicalsiteIFC only (plumbing in IFC is not as built)
ASSUMED
HVACDOAS unitsAlpha Aire (by AllTrade Heating and Air)Alpha Aire II DOAS, VAV air-source heat pump w/ energy recovery, 8 ton3Mechanical + home locker roommanualAllTrades DOAS invoice; Reed emails 8/17 + 9/8/26
HVACOther HVACTrane / Greenheck (IFC)Trane 5 ton; Greenheck IDBHper IFCIFC families
ASSUMED
HVACDryer exhaust upgradeLoomis Bros. Equipment Co. (Clean Cycle / Greenheck)Clean Cycle LLM-8-12-i Lint Lasso (8" in / 12" out, 1,200 CFM, 200 micron sock, pressure switch alarm); Greenheck BSQ-90 inline fan 1.5 HP, 1,000 CFM @ 1.25" SP, 230V 3P; Clean Cycle FC-HOA fan control w/ dryer interlock1 setLaundryLoomis proposal TW100226-OPP808B (signed 10/20/26); Reed Tarr email 10/26/26
Approved
ElectricalExterior LED wall packsGreentek Energy SystemsSWP5 LED semi-cutoff wall pack, wattage-tunable 60/50/40W, selectable CCT 3000/4000/5000K, photocell; P/N GT-SWP5-60W-LBCGDP-aCCTbc-D-W5+Exteriorsite · manualReed Tarr email 10/26/26
ElectricalEmergency lightsKonliteJLEU9RC LED emergency light with battery backup (remote-capable), 120/277V, 2.4W, max 24 hr rechargeAt exitsInterior exitsmanualReed Tarr email 10/26/26
FF&ELocker room clocksNevcoModel TBD (not in the CAH install bid)3 (per CAH bid)Locker roomssiteNevco thread 7/29-8/24/26; CAH Custom Installs bid 3/12/26; Reed Tarr email 10/26/26
Model TBD; installed by CAH Custom Installs (Andrew Hoffman)
FF&ETVsNot on file60" flat screen wall mount (IFC); locker TVs mirror one PC. No TV models available (Reed).per IFCLocker rooms, coaches roomIFC; Will Miers 8/31/26
Make/model not available
FF&EIce machineManitowociP0450 half-dice/dice cube machine (IDP0450A ASSUMED)1Training 132site · manualIce Machine Specs - 132 Training
ASSUMED
FF&EReach-in refrigeratorEverest Refrigeration (ASSUMED brand)EGSDH2 glass/solid half-door dual tempStainless1Training 132manualRefrigerator Specs - 132 Training
ASSUMED
FF&EWall graphicsDG Graphics (Martinsville)Vinyl wall wrap + window perf on door glassSchool colorsHallway north of locker room, doorsDG Graphics thread 7/21-8/24/26
FF&EWasher / dryerMilnorWasher: Milnor 30022T6X 60 lb rigid-mount washer-extractor. Dryer: Milnor M758V 75 lb OPL dryer (dryer spec: docs/Dryer-Milnor-M758V.pdf)1 + 1LaundrymanualReed Tarr email 10/26/26
FF&EBenches (visitor locker)Lee CompanyPortable anchorless pedestal benchesVisitor locker roomReed 9/14/26
Model ASSUMED
FF&EFire extinguishers + cabinetsExtinguisher Pro (owner)Per Building C fire extinguisher planPer planFootball Locker room thread 9/1/26
By owner
SiteWrought iron fence + gatesParker Fencing, Camby, INOrnamental (wrought iron) fence, main gatesBlack ASSUMEDSite perimeterReed emails 8/19, 9/8, 10/12/26; Reed Tarr email 10/26/26
Model and color not on file (Black ASSUMED)
SiteChain link privacy fenceK W Fence (Earl Wagler)Chain link around HVAC units + electrical serviceGalvanized ASSUMEDHVAC + electricalReed "Fw: invoice" 10/20/26
SiteConcrete parking curbsBroyer ConstructionPrecast wheel stops, pinned, ~24" to center from walk (Kyle)Concreteall stallsParkingAFC Floors thread 10/8-10/15/26
Spacing ASSUMED
SiteArtesian Well + mumsBroyer / landscape crewTwo-tier rock well, bucket + landscape pump; alternating red & yellow mumsRed / yellowSouth lawnUpdate from the AFC thread 9/2-9/8/26

Warranties

ItemWarrantorTermStartRegistrationDocument
Building C work (general 1-yr correction)GT Investments, LLC1 year correction period after Substantial Completion; all other warranties issued in Owner name2026-08-26n/aAIA A104 Contract (Owner GM Development) §9.4, §18.2
Metal roof panelsGraber Post Buildings (manufacturer)40 year (G-Rib 40 Yr 29 ga), confirmed by Reed 10/26/262026-08-26Not on file - ask GPBGPB contract #71682
Wainscot / liner panelsGraber Post Buildings10 year (G10 10 Yr 29 ga), confirmed by Reed 10/26/262026-08-26Not on fileGPB contract #71682
GPB building workmanshipGraber Post Buildings, Inc.Limited: correct deficiencies; claims within 1 year of Substantial Completion (confirmed by Reed 10/26/26)2026-08-26n/aGPB contract #71682 §17, §28
Access control, cameras, networkAPTEK1 year hardware + labor from installationInstall date not on filen/aAPTEK quotes #002421 / #002495
Baby changing stationASI (American Specialties)ASI 9012 term not on file2026-06/07 deliveryNot on fileTotal Restroom TR-303115856 (2 x ASI 9012 installed)
Water softenerCulliganManufacturer warranty - term not on file2026-05-27 ASSUMEDNot on fileCulligan inv. 6489609; Hi-Flo 3e IOM
DOAS unitsAlpha Aire / AllTrade Heating and AirTerm not on fileStartup 2026-09 ASSUMEDNot on fileAsk AllTrades
MEP installationAllTrade Heating and AirTerm not on file (assume 1 yr per prime contract)2026-08-26 ASSUMEDn/aAllTrades proposal #101 (no warranty clause)
Epoxy flake floorsTAK Floor CoatingsTerm not on file (sticky floor in officials RR under review 10/2026)2026-06-19 ASSUMEDn/aTAK invoice #75
Carpet tileMillikenManufacturer warranty - term not on file2026-07-25 ASSUMEDNot on fileWagler inv. 4419
Flush valvesSloanSloan G2 8111-1.6 / 8186-1.0: manufacturer warranty - term not on file2026-10 (replacement) ASSUMEDNot on fileReed 10/5/26
SignageSign manufacturer (spec)5 years from Substantial Completion (Div 10 spec)2026-08-26 ASSUMEDn/aBuilding C Div 10 spec §1.6 (signs by owner/Sign Solutions - ASSUMED)
MasonryL&L Masonry LLCTerm not on file (1 yr ASSUMED)2026-08 ASSUMEDn/aNo warranty language in L&L quote
Site work / fence / pavingBroyer ConstructionTerm not on file; fence (Parker Fencing) "as provided by manufacturer" (Div 32)2026-10 ASSUMEDn/aBuilding C Div 32 spec; Broyer contracts
Dryer lint trap + inline blowerLoomis Bros. Equipment Co. / Clean Cycle SystemsLoomis 90-day limited labor; Clean Cycle 1-year parts on lint filter products; equipment typically 1 yr parts per Loomis termsShip/install date not on filen/aLoomis proposal TW100226-OPP808B
Emergency lightsKonlite3-year limitedInstall date not on fileNot on fileKonlite JLEU9RC spec screenshot
Washer + dryerMilnorManufacturer warranty - term not on fileNot on fileNot on fileMilnor 30022T6X / M758V spec sheets

Subcontractors & suppliers

CompanyTradeContact
GT Investments, LLC (Brook / Reed Tarr)General contractorReed Tarr, reed@dbtarr.com; Brook Tarr, brook@dbtarr.com; 812-278-0060
D B Tarr and CompanyArchitect / plans8728 W Co Rd 175 S, French Lick IN; dbtarr@yahoo.com; 812-278-0060
GM Development Companies LLCOwner rep / developer (contract owner)Greg Martz, greg@gm-development.com, 317-417-5094
Graber Post Buildings, Inc. (GPB)Building shell, metal roof/siding/trim, toilet partitions orderDarrell Wittmer, 812-636-7355, graberpost.com
L&L Masonry LLCCMU walls, brick wainscotLamar Fox, LLMasonryllc@gmail.com, 317-512-8908
AllTrade Heating and AirElectrical, mechanical, plumbing, DOASJosh (sales); Jacque Kendle, admin@alltradeheatingandair.net, 812-789-3065
Broyer Construction (Jack Broyer)Site demo, utilities, concrete, asphalt, fence install, landscapingJack Broyer, 765-318-2098
W & W Poured Walls, Inc.Concrete cut + pour back (interior)Sheldon Graber, sheldon@wwpouredwalls.com, 812-787-0180
TAK Floor CoatingsEpoxy flake floors + polished concretesales@takcoatings.com, 317-300-5017
Wagler Floor & DesignCarpet tile + cove baseMatt Wagler, Matt@waglerfloor.com, 812-257-0700
Matthew KneppBlock showers (softball locker room)mattslk@upwardmail.com
K W Fence (Earl Wagler)Chain link privacy fencingkwfence1@gmail.com
K and K Fence CoTemporary fence panels (supply)Kevin Banholzer, kbanholzer@kandkfence.com, 317-759-5891
Culligan Martinsville / Culligan UltrapureWater softener supply + installJason Alexander, 317-441-9242; 765-349-5351
Stoll Bros. LumberSolid surface countertops (measure + install)812-636-4053
Cabinets To Go (Indianapolis)CabinetsTimothy Casteel, 317-608-0165
Indiana Door & Hardware SpecialtiesDoor hardware812-336-0813
CDF DistributorsHM doors, frames, mullionscdfdistributors.com
Total RestroomToilet accessories supplytotalrestroom.com
Grabbars.comGrab bars supplygrabbars.com
APTEKAccess control, cameras, networking (GM Development contract)Damir Husejnovic, DamirH@aptek-ssc.com, 317-643-2726
Galaxy OneLow voltage / fiberJames Meade, james.meade@galaxyone.us
Live Wire Consulting, Inc. (LWC Electrical & Communications)Lower electrical box N of ticket boothTom Walls, 1210 E Washington St, Martinsville, IN 46151; (765) 792-4012; www.lwc-electrical.com
DG GraphicsWall graphics + window perfMatt Long, matt@dggraphicsindy.com, 765-349-9500
Nevco (clocks) / CAH Custom Installs (installer)Locker room clocks: supply (Nevco) + installAndrew Hoffman, CAH Custom Installs, 6947 State Rd. 39, Martinsville, IN 46151; (812) 327-7652; cahcustominstalls@gmail.com
HilarioPainter (also extra cleaning)Hilario, 502-931-4118
Loomis Bros. Equipment Co.Dryer lint trap (Clean Cycle) + inline blower (Greenheck) supplyTroy Willis, (317) 432-2648, twillis@loomisbros.com; 409 Biltmore Dr, Fenton, MO 63026; 800-783-6665
Parker Fencing (Camby, IN)Wrought iron fenceContact not in sources
Lee CompanyVisitor locker room benches (per Reed 9/14/26)Samantha Broach (billing), sbroach@leecompanyinc.com, 812-235-8155
Extinguisher ProFire extinguishers (owner contract)Via Kyle Stout
Sign Solutions (Indianapolis)Signage (owner)Via Kyle Stout - ASSUMED

Assumptions

Open items

  1. Brick: which brick (maker, name, color) did L&L Masonry use to "match existing building"? (Reed will send separately)
  2. Nevco clock model: not in the CAH install bid; still TBD.
  3. Paint: the SW color number for "GPB Grey", and where the Duct Blue / Positive Red accent walls are.
  4. Partitions: was Dark Blue the final color?
  5. Warranty documents and registrations for Culligan, Alpha Aire, Sloan, Milliken, TAK, AllTrades, Milnor, ASI and Loomis.
  6. Wrought iron fence (Parker Fencing): model and color? Was the parking curb spacing confirmed at 24" to center?
  7. Fire extinguisher cabinet type.
  8. Parker Fencing contact details.